They are moving at a snail's pace and closing has been pushed back a few times, but we are getting there! Last Monday, they put in the crown molding, Friday they put in the cabinets, and Saturday they stained them. They look pretty!

Moldings
 Butler Pantry
 Kitchen (from Living Room)
 Kitchen (from Breakfast Area)
 Living Room (quarter rounds against the wall)

 Master Bathroom
 Guest Bathroom


Our new closing date is December 5th. But, they still have to do the following:

  1. Install the master tub and sinks
  2. Tile the bathrooms and kitchen
  3. Put in all the plumbing fixtures, door fixtures, electrical outlet covers
  4. Put in inside AND outside lighting and smoke alarms
  5. Put in granite counters
  6. Paint the walls
  7. Paint the trim
  8. Put in floor moldings
  9. Paint the moldings
  10. Put stone around fireplace and connect it to gas line
  11. Put in appliances
  12. Put in our blinds
  13. Put in tile floors and carpet
  14. Brick the house (yep, still haven't done that!)
  15. Put in the driveway and walkway
  16. Put in the landscaping
  17. Put in the front sidewalk
  18. Put up our fence
  19. Clean
  20. and Inspect.


No big deal :(